Hebbal Bus Depot, Bengaluru.

Ninety-six bays under one steel canopy, a washing line that drains in the wrong direction had to be rebuilt in month two, and a staff block that the drivers actually use.

ClientBMTC
Completed2023
Bays96
Site4.2 acres
Bus depot with a long steel canopy at dawn
Fig. 02 The canopy from the north-east, 5.40am. Bays 1–24 in use. 13°02′N 77°35′E

A depot is a queue with weather.

Buses arrive, get washed, get fuelled, get parked, and leave in a sequence that cannot be delayed by architecture. The brief was 96 bays, a workshop, a washing line, and a staff block for 340 drivers on shift change.

Our proposal was one canopy instead of four blocks, so a driver can walk from any bay to the office without crossing the yard in the rain.

Steel, and a lot of gutters.

Bolted steel connection detail The depot canopy from a distance

330 metres of canopy, 96 bays at 12.4 m centres. The columns land between bays so no bus reverses into one, and every third column carries a gutter downpipe that drains to the south, away from the workshop doors.

What we got wrong.

The washing line was built at a 1.2% fall in the wrong direction, so the water pooled at the entrance to the workshop. It was a drawing error, not a site error — we had mirrored a detail from another project.

We rebuilt 40 metres of channel in month two at our cost. The lesson went into the office standards: drainage fall is now dimensioned on the plan, not implied on the section.

Specification.

StructureStructural steel canopy, 330 m, galvanised, bolted
RoofInsulated metal deck, 75 mm PUF, standing seam
Bays96 at 12.4 m centres, 3.6 m clear height
Workshop7 bays, pit inspection, overhead crane rail
Staff block1,150 sq m, two floors, rest rooms and canteen
ContractDesign and build with a single contractor
CompletionMarch 2023, five weeks late after the drainage rebuild